QTV - In 2018, Ha Nam Dyke is upgraded with 5 more km, contributing to improving the capacity of storm and tide resistance, local people’s life and property.
 

a
The construction site

Quang Ninh’s Department of Agriculture and Rural Development, as the investor, has required contractors to hasten the construction progress. The project of upgrading Ha Nam Dyke in Quang Yen Town has a total investment of more than 400 billion VND. It is divided into different stages and carried out in years. Once completed, the dyke is capable of withstanding storm level 10 combined with tide frequency of 5%. This year, it is expected to concrete 5 more km out of the total of 33.65km in length. Weak points will be strengthened this year and beyond, ensuring safety for local people to live and work.  