Strengthening the assurance of work safety and construction quality of Halong – Van Don Highway

Friday, Aug 04 2017, 13:10
.

QTV - Ha Long - Van Don Highway project plays an important role in socio-economic development of Quang Ninh. Apart from ensuring the progress of the project, the labor safety and construction quality are also being focused by the investors and contractors.

After the collapse of the girder bridge on July 28th, investor of the project - BOT Bien Cuong Joint Stock Company – had reviewed the construction progress of the contractors and requested them to ensure labor safety and quality of these works.
After the collapse of the girder bridge on July 28th, investor of the project - BOT Bien Cuong Joint Stock Company – had reviewed the construction progress of the contractors and requested them to ensure labor safety and quality of these works.

The Package 6 of Ha Long - Van Don highway project was implemented by Truong Son Construction and Investment Joint Stock Company, including 4 large bridges. Due to high construction conditions, the labor safety is always strictly enforced. By now, this package has been on schedule. After the collapse of the girder bridge on July 28th, investor of the project - BOT Bien Cuong Joint Stock Company – had reviewed the construction progress of the contractors and requested them to ensure labor safety and quality of these works. Ha Long - Van Don Highway project has the length of 53.6 km, by now, the project has carpeted 6km asphalt road surface. Ensuring labor safety, quality of construction are important factors to ensure the progress of the project.
Translated by Chu Linh

;