QTV - Such projects as Van Don International Airport, high-end class resort, and 15km long road from the airport to the resort have been hastened to ensure their progress. 
 

a
Quang Ninh Party Committee Secretary Nguyen Van Doc encouraged workers at construction site for Van Don International Airport

As for Van Don International Airport, its terminal, 2nd phase, with total usable floor area of 25,400 m2, has its roof and glass competed. More than 1,500 staff, engineers, and workers are finishing final touches to have a calibration flight on July 10th, As for Van Don Resort covering an area of 71 ha, construction has been covered on 5 ha. Also in the locality, contractors have mobilized human resources to speed up the construction of 15 km long road connecting the airport with the resort, ensuring a complete transport infrastructure. 
Translated by Quynh Trang

 
  
;