15 km main road project in Van Don accelerated

Saturday, Apr 14 2018, 08:41
.

QTV - With the aim of completing in Dec., 2018, 4 months earlier than the plan, the main road project from Van Don International Airport to luxury resort-entertainment complex in Van Don is being accelerated by the Department of Transport, as the investor, and contractors.
With a length of 15km, the main road project from Van Don International Airport to luxury resort-entertainment complex in Van Don has a total investment of 1.4 tri.VND. The project has 4 lanes with the 24 m wide road surface, trees and electricity. Started the construction in Nov.,2017, to date the project ensures the set schedule. Despite difficulties, the Department of Transport and Olympia Co.Ltd. are determined to complete the above project in Dec. 2018. Once operational, the project will synchronously connect infrastructure, contributing to the construction and development of Van Don Special Administrative Economic Zone.
Translated by Thu Giang

 
;