Bach Dang Bridge to be segmentally enclosured prior to Apr 30th

Monday, Mar 12 2018, 11:20
.

QTV - Under the requirement of provincial authority, Bach Dang Bridge will be enclosure prior to Apr 30th 2018. To ensure its progress, contractors are hastening the remaining tasks. 
 

az
Bach Dang Bridge

XL04 and XL05 packages under taken by E&C Trung Nam Company has been carried out in spite of Tet Holiday so balanced cantilever at piers have basically completed. Main bridge packages are urgently constructed. However bridge header and intersection packages do not meet construction progress. After Tet Holiday, XL06 package undertaken by Cuong Thinh Thi contractor and XL08 package by Phuc Loc contractor was lag behind the construction plan due to the shortage of workers. To ensure the enclosure prior to Apr 30th, investors and contractors need to make more efforts in term of human resources and  machinery or even start an emulation movement to reach the finish line. 
Translated by Quynh Trang

 

;